Star Dairy Solar
ERCOT-25INR0164BetaActiveSolarERCOTLBNL + Live
125.61 MW generation in Lamar, TX · In queue since November 2022 · Proposed COD April 2027
125.61 MW
Capacity
1
Components
Solar
3y 5m
In Queue
IA Executed
IA Status
Signed Dec 2024
Interconnection Timeline
Queue → IA
2y 1m
IA → COD
2y 4m
Total Duration
2y 1m
Construction75%
Queue EntryNov 23, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementDec 9, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-04-03
Project Details
State
TX
County
Lamar
Region
ERCOT
Developer
Star Dairy Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 1692 PARIS_SW1_5 -- 11699 WOODARD_5
Data Source
LBNL + Live