Nymphaea Solar
BetaActiveSolarERCOTLBNL + Live
120.9 MW generation in Wichita, TX · In queue since September 2022 · Proposed COD July 2028
120.9 MW
Capacity
1
Components
Solar
3y 6m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 10m
Facilities Study50%
Queue EntrySep 21, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-07-01
Project Details
State
TX
County
Wichita
Region
ERCOT
Developer
Nymphaea Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV 1730 Krum West Swtich - 6111 Riley7B
Data Source
LBNL + Live