Blue Heron BESS — Project Summary

Queue ID
ERCOT-25INR0146
Capacity
201.08 MW
Technology
Battery
Status
active
Location
Reeves, TX
Region
ERCOT
Developer
Blue Heron BESS, LLC
IA Status
Facility Study

Blue Heron BESS

BetaActiveBatteryERCOTLBNL + Live

201.08 MW storage in Reeves, TX · In queue since October 2022 · Proposed COD March 2028

201.08 MW

Capacity

1

Components

Battery

3y 5m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

5y 5m

Facilities Study50%
Queue EntryOct 24, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-03-31

Project Details

State

TX

County

Reeves

Region

ERCOT

Developer

Blue Heron BESS, LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap 138kV MANSON (1094) - Riverton (11083)

Data Source

LBNL + Live