Dolce BESS
BetaActiveBatteryERCOTLBNL + Live
100.65 MW storage in Mitchell, TX · In queue since September 2022 · Proposed COD January 2028
100.65 MW
Capacity
1
Components
Battery
3y 6m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 4m
Facilities Study50%
Queue EntrySep 27, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-01-31
Project Details
State
TX
County
Mitchell
Region
ERCOT
Developer
Dolce BESS, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV 1189 BARBER_LK1_8 - 19520 CHINAGRVX2_8
Data Source
LBNL + Live