Champaign BESS
ERCOT-25INR0138BetaActiveBatteryERCOTLBNL + Live
201.13 MW storage in Glasscock, TX · In queue since September 2022 · Proposed COD June 2027
201.13 MW
Capacity
1
Components
Battery
3y 7m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 9m
Facilities Study50%
Queue EntrySep 21, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-06-28
Project Details
State
TX
County
Glasscock
Region
ERCOT
Developer
Champaign BESS, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV Shaw POD (18664) _x0013_ Desert Wind Sub (11222) new station Potterson Lake Switch
Data Source
LBNL + Live
Linked EIA Plant
Champaign BESS, LLC
EIA Plant ID: 67917
No news available for this project.