August Draw Energy
ERCOT-25INR0112BetaActiveSolarERCOTLBNL + Live
250 MW generation in Reeves, TX · In queue since September 2022 · Proposed COD June 2028
250 MW
Capacity
1
Components
Solar
3y 7m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 9m
Facilities Study50%
Queue EntrySep 15, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-06-27
Project Details
State
TX
County
Reeves
Region
ERCOT
Developer
DBR Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 60207 Verhalen _x0013_ 60808 Hoefs Road
Data Source
LBNL + Live
No news available for this project.