Sun Cactus Solar
ERCOT-25INR0109BetaActiveSolarERCOTLBNL + Live
120.63 MW generation in Duval, TX · In queue since July 2022 · Proposed COD October 2027
120.63 MW
Capacity
1
Components
Solar
3y 9m
In Queue
IA Executed
IA Status
Signed Nov 2023
Interconnection Timeline
Queue → IA
1y 4m
IA → COD
3y 11m
Total Duration
1y 4m
Construction75%
Queue EntryJul 5, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementNov 6, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-10-15
Project Details
State
TX
County
Duval
Region
ERCOT
Developer
Sun Cactus Solar Project, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 138kV 8510 Falfurrias - 8695 Crestonio
Data Source
LBNL + Live