Luthor Solar
BetaActiveSolarERCOTLBNL + Live
101 MW generation in Howard, TX · In queue since June 2022 · Proposed COD September 2027
101 MW
Capacity
1
Components
Solar
3y 9m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5y 3m
Facilities Study50%
Queue EntryJun 27, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-09-25
Project Details
State
TX
County
Howard
Region
ERCOT
Developer
TREX US Luthor LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV 23831 Luther Station _x0013_ 10032 Little Luther
Data Source
LBNL + Live
No news available for this project.