Elio BESS
317.2 MW storage in Brazoria, TX · In queue since July 2022 · Proposed COD August 2027
317.2 MW
Capacity
1
Components
Battery
3y 9m
In Queue
IA Executed
IA Status
Signed Sep 2024
Queue → IA
2y 2m
IA → COD
2y 11m
Total Duration
2y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2027-08-05
State
TX
County
Brazoria
Region
ERCOT
Developer
Elio Energy LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 42980 Nash - 44010 Wa Parish circuit 02
Data Source
LBNL + Live
Linked EIA Plant
Elio Energy LLC
EIA Plant ID: 65850