Goldeneye BESS
ERCOT-25INR0100BetaActiveBatteryERCOTLBNL + Live
201.6 MW storage in Bell, TX · In queue since June 2022 · Proposed COD May 2028
201.6 MW
Capacity
1
Components
Battery
3y 10m
In Queue
IA Executed
IA Status
Signed Feb 2024
Interconnection Timeline
Queue → IA
1y 8m
IA → COD
4y 3m
Total Duration
1y 8m
Construction75%
Queue EntryJun 10, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementFeb 26, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2028-05-15
Project Details
State
TX
County
Bell
Region
ERCOT
Developer
Black Mountain Energy Storage II
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
3423 KILLEEN Switch 138 KV
Data Source
LBNL + Live
No news available for this project.