Soleil Storage
BetaActiveBatteryERCOTLBNL
301.64 MW storage in Clay, TX · In queue since September 2022 · Proposed COD October 2027
301.64 MW
Capacity
1
Components
Battery
3y 6m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5y 1m
Facilities Study50%
Queue EntrySep 2, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-10-01
Project Details
State
TX
County
Clay
Region
ERCOT
Developer
Soleil Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345 kV 1730 Krum West Switch - 6111 Riley ckt 2
Data Source
LBNL
No news available for this project.