Soleil Storage — Project Summary

Queue ID
ERCOT-25INR0098
Capacity
301.64 MW
Technology
Battery
Status
active
Location
Clay, TX
Region
ERCOT
Developer
Soleil Solar, LLC
IA Status
Facility Study

Soleil Storage

BetaActiveBatteryERCOTLBNL

301.64 MW storage in Clay, TX · In queue since September 2022 · Proposed COD October 2027

301.64 MW

Capacity

1

Components

Battery

3y 6m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

5y 1m

Facilities Study50%
Queue EntrySep 2, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-10-01

Project Details

State

TX

County

Clay

Region

ERCOT

Developer

Soleil Solar, LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap 345 kV 1730 Krum West Switch - 6111 Riley ckt 2

Data Source

LBNL

No news available for this project.