SanPat Solar I
ERCOT-25INR0081BetaActiveSolarERCOTLBNL + Live
308.88 MW generation in San Patricio, TX · In queue since July 2022 · Proposed COD July 2027
308.88 MW
Capacity
1
Components
Solar
3y 9m
In Queue
IA Executed
IA Status
Signed Oct 2023
Interconnection Timeline
Queue → IA
1y 3m
IA → COD
3y 9m
Total Duration
1y 3m
Construction75%
Queue EntryJul 18, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementOct 18, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-07-08
Project Details
State
TX
County
San Patricio
Region
ERCOT
Developer
Padre Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 8249 Angstrom _x0013_ 8659 Naismith
Data Source
LBNL + Live
No news available for this project.