Peregrine BESS 2
BetaActiveBatteryERCOTLBNL + Live
150 MW storage in Goliad, TX · In queue since August 2022 · Proposed COD July 2027
150 MW
Capacity
1
Components
Battery
3y 7m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 11m
Facilities Study50%
Queue EntryAug 5, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-07-01
Project Details
State
TX
County
Goliad
Region
ERCOT
Developer
CED Development Inc.
Utility
—
Entity
ERCOT
Point of Interconnection
8673 RAPTOR7A 345kV
Data Source
LBNL + Live
No news available for this project.