Saltillo Storage — Project Summary

Queue ID
ERCOT-25INR0073
Capacity
101 MW
Technology
Battery
Status
active
Location
Bastrop, TX
Region
ERCOT
Developer
SALTILLO STORAGE
IA Status
Facility Study

Saltillo Storage

BetaActiveBatteryERCOTLBNL

101 MW storage in Bastrop, TX · In queue since May 2022 · Proposed COD June 2026

101 MW

Capacity

1

Components

Battery

3y 10m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4y 1m

Facilities Study50%
Queue EntryMay 10, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-06-01

Project Details

State

TX

County

Bastrop

Region

ERCOT

Developer

SALTILLO STORAGE

Utility

Entity

ERCOT

Point of Interconnection

7331 Cedarhill Substation 138kV

Data Source

LBNL