Saltillo Storage
BetaActiveBatteryERCOTLBNL
101 MW storage in Bastrop, TX · In queue since May 2022 · Proposed COD June 2026
101 MW
Capacity
1
Components
Battery
3y 10m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
4y 1m
Facilities Study50%
Queue EntryMay 10, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-06-01
Project Details
State
TX
County
Bastrop
Region
ERCOT
Developer
SALTILLO STORAGE
Utility
—
Entity
ERCOT
Point of Interconnection
7331 Cedarhill Substation 138kV
Data Source
LBNL