Albatross BESS
BetaActiveBatteryERCOTLBNL + Live
50.4 MW storage in Mclennan, TX · In queue since May 2022 · Proposed COD February 2028
50.4 MW
Capacity
1
Components
Battery
3y 10m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 9m
Facilities Study50%
Queue EntryMay 16, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-02-22
Project Details
State
TX
County
Mclennan
Region
ERCOT
Developer
Albatross Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
From Bus #165 Windsor Switch To Bus #161 McGregor
Data Source
LBNL + Live
No news available for this project.