Argenta Solar
ERCOT-25INR0060BetaActiveSolarERCOTLBNL + Live
270 MW generation in Bee, TX · In queue since June 2022 · Proposed COD June 2028
270 MW
Capacity
1
Components
Solar
3y 10m
In Queue
IA Executed
IA Status
Signed Apr 2024
Interconnection Timeline
Queue → IA
1y 10m
IA → COD
4y 2m
Total Duration
1y 10m
Construction75%
Queue EntryJun 27, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementApr 5, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2028-06-30
Project Details
State
TX
County
Bee
Region
ERCOT
Developer
Charter Oak Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 8689 Tango - 8606 Goddard
Data Source
LBNL + Live