SanPat Solar II
ERCOT-25INR0052BetaActiveSolarERCOTLBNL + Live
256.23 MW generation in San Patricio, TX · In queue since February 2022 · Proposed COD July 2027
256.23 MW
Capacity
1
Components
Solar
4y 2m
In Queue
IA Executed
IA Status
Signed Oct 2023
Interconnection Timeline
Queue → IA
1y 8m
IA → COD
3y 9m
Total Duration
1y 8m
Construction75%
Queue EntryFeb 28, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementOct 18, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-07-22
Project Details
State
TX
County
San Patricio
Region
ERCOT
Developer
CGRP 04, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 8249 Angstrom _x0013_ 8659 Naismith
Data Source
LBNL + Live