Blue Skies BESS — Project Summary

Queue ID
ERCOT-25INR0046
Capacity
306.26 MW
Technology
Battery
Status
active
Location
Hill, TX
Region
ERCOT
Developer
ACTX BESS Project LLC
IA Status
IA Executed

Blue Skies BESS

ERCOT-25INR0046BetaActiveBatteryERCOTLBNL + Live

306.26 MW storage in Hill, TX · In queue since May 2022 · Proposed COD December 2027

306.26 MW

Capacity

1

Components

Battery

3y 11m

In Queue

IA Executed

IA Status

Signed Aug 2024

Interconnection Timeline

Queue → IA

2y 3m

IA → COD

3y 4m

Total Duration

2y 3m

Construction75%
Queue EntryMay 10, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementAug 12, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2027-12-31

Project Details

State

TX

County

Hill

Region

ERCOT

Developer

ACTX BESS Project LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

68090 SAM SW 345kV

Data Source

LBNL + Live

No news available for this project.