Findley Solar
BetaActiveSolarERCOTLBNL + Live
50.34 MW generation in Limestone, TX · In queue since October 2021 · Proposed COD January 2028
50.34 MW
Capacity
1
Components
Solar
4y 5m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
6y 3m
Facilities Study50%
Queue EntryOct 5, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-01-01
Project Details
State
TX
County
Limestone
Region
ERCOT
Developer
Gransolar Texas Sixteen, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
107 Prairie Hill 69 kV
Data Source
LBNL + Live
No news available for this project.