Yellow Cat Wind
ERCOT-25INR0018BetaActiveWindERCOTLBNL + Live
301.2 MW generation in Navarro, TX · In queue since August 2021 · Proposed COD April 2027
301.2 MW
Capacity
1
Components
Wind
4y 8m
In Queue
IA Executed
IA Status
Signed Jul 2024
Interconnection Timeline
Queue → IA
2y 11m
IA → COD
2y 9m
Total Duration
2y 11m
Construction75%
Queue EntryAug 17, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementJul 9, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2027-04-01
Project Details
State
TX
County
Navarro
Region
ERCOT
Developer
Yellow Cat Wind LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 1906 Venus - 68091 Navarro
Data Source
LBNL + Live
No news available for this project.