Nockenut Springs Solar 3 — Project Summary

Queue ID
ERCOT-25INR0010
Capacity
203.39 MW
Technology
Solar
Status
active
Location
Gonzales, TX
Region
ERCOT
Developer
Pecan Springs Energy, LLC
IA Status
Facility Study

Nockenut Springs Solar 3

BetaActiveSolarERCOTLBNL + Live

203.39 MW generation in Gonzales, TX · In queue since September 2020 · Proposed COD June 2029

203.39 MW

Capacity

1

Components

Solar

5y 6m

In Queue

Facility Study

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

8y 9m

Facilities Study50%
Queue EntrySep 25, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-06-05

Project Details

State

TX

County

Gonzales

Region

ERCOT

Developer

Pecan Springs Energy, LLC

Utility

Entity

ERCOT

Point of Interconnection

tap 345kV 5133 Elm Creek - 5915 STP ckt 1

Data Source

LBNL + Live