BasRanch (TEF - Due Diligence)
ERCOT-25INR0008BetaActiveGasERCOTLBNL + Live
1,350 MW generation in Ward, TX · In queue since August 2020 · Proposed COD December 2028
1,350 MW
Capacity
1
Components
Gas
5y 8m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
8y 4m
Facilities Study50%
Queue EntryAug 4, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-01
Project Details
State
TX
County
Ward
Region
ERCOT
Developer
CPV Basin Ranch, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV Riverton Switch - Sand Lake Switch