Tokyo TxHSR TPSS EW-1
BetaActiveOtherERCOTLBNL + Live
50 MW generation in Ellis, TX · In queue since January 2019 · Proposed COD July 2028
50 MW
Capacity
1
Components
Other
7y 2m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
9y 6m
Facilities Study50%
Queue EntryJan 30, 2019
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-07-15
Project Details
State
TX
County
Ellis
Region
ERCOT
Developer
Texas Central Rail Holdings, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap 138kV 2241 Ennis W - 2321 Waxahachie
Data Source
LBNL + Live
No news available for this project.