Prairie Creek BESS
BetaActiveBatteryERCOTLBNL
9.95 MW storage in Dallas, TX · In queue since January 2024 · Proposed COD June 2025
9.95 MW
Capacity
1
Components
Battery
2y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
1y 5m
Schedule
10 months past proposed COD
In Study38%
Queue EntryJan 25, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-06-01
Project Details
State
TX
County
Dallas
Region
ERCOT
Developer
SMT Dallas LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Station Name: PRCK Load Name: LDLXFMR4 XFMR Number: 4 Bus number: 2762 Voltage: 138 kV
Data Source
LBNL
No news available for this project.