Anemoi Energy Storage Repowering
BetaActiveBatteryERCOTLBNL
5 MW storage in Hidalgo, TX · In queue since October 2023 · Proposed COD February 2025
5 MW
Capacity
1
Components
Battery
2y 5m
In Queue
Facility Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
1y 4m
Schedule
13 months past proposed COD
Facilities Study50%
Queue EntryOct 30, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-02-28
Project Details
State
TX
County
Hidalgo
Region
ERCOT
Developer
Anemoi Energy Storage, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
8574 POMELO 345kV
Data Source
LBNL