Cedro Hill Wind Repower
ERCOT-24INR0632BetaActiveWindERCOTLBNL + Live
9.93 MW generation in Webb, TX · In queue since September 2023 · Proposed COD April 2026
9.93 MW
Capacity
1
Components
Wind
2y 7m
In Queue
IA Executed
IA Status
Signed Sep 2009
Interconnection Timeline
IA → COD
16y 7m
Total Duration
2y 7m
Schedule
0 months past proposed COD
Construction75%
Queue EntrySep 28, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementSep 9, 2009
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2026-04-01
Project Details
State
TX
County
Webb
Region
ERCOT
Developer
CEDRO HILL WIND LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
80439 LA QUINTA 138kV
Data Source
LBNL + Live
No news available for this project.