Champion Wind Repower
ERCOT-24INR0627BetaActiveWindERCOTLBNL + Live
0.31 MW generation in Nolan, TX · In queue since September 2023 · Proposed COD May 2025
0.31 MW
Capacity
1
Components
Wind
2y 7m
In Queue
IA Executed
IA Status
Signed Jan 2007
Interconnection Timeline
IA → COD
18y 4m
Total Duration
2y 7m
Schedule
11 months past proposed COD
Construction75%
Queue EntrySep 25, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementJan 19, 2007
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2025-05-09
Project Details
State
TX
County
Nolan
Region
ERCOT
Developer
Champion Wind Farm, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Bus# 1048 - Tonkawa
Data Source
LBNL + Live
No news available for this project.