GridGuardian BESS
BetaActiveBatteryERCOTLBNL
227.99 MW storage in Bell, TX · In queue since September 2023 · Proposed COD April 2027
227.99 MW
Capacity
1
Components
Battery
2y 6m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 7m
Facilities Study50%
Queue EntrySep 22, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-04-19
Project Details
State
TX
County
Bell
Region
ERCOT
Developer
SMT Temple BESS LLC
Utility
—
Entity
ERCOT
Point of Interconnection
3412 TEMPLE PECAN CREEK 345kV
Data Source
LBNL