Pirate BESS
9.8 MW storage in San Patricio, TX · Proposed COD June 2025
9.8 MW
Capacity
1
Components
Battery
—
In Queue
IA Executed
IA Status
Signed Sep 2023
IA → COD
1y 9m
Schedule
10 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2025-06-01
State
TX
County
San Patricio
Region
ERCOT
Developer
Regis Sinton-Pirate, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Station Name (TSP Station Code): Pirate (5218) Load/Load Transformer Name: R1 PTI Bus Number: 8652 Voltage in kV (Transmission Level): 69 kV
Data Source
LBNL