Houston IV BESS — Project Summary

Queue ID
ERCOT-24INR0584
Capacity
168.6 MW
Technology
Battery
Status
active
Location
Harris, TX
Region
ERCOT
Developer
SMT Houston IV LLC
IA Status
IA Executed

Houston IV BESS

ERCOT-24INR0584BetaActiveBatteryERCOTLBNL + Live

168.6 MW storage in Harris, TX · In queue since July 2023 · Proposed COD June 2026

168.6 MW

Capacity

1

Components

Battery

2y 9m

In Queue

IA Executed

IA Status

Signed Nov 2024

Interconnection Timeline

Queue → IA

1y 4m

IA → COD

1y 7m

Total Duration

1y 4m

Construction75%
Queue EntryJul 10, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementNov 7, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2026-06-03

Project Details

State

TX

County

Harris

Region

ERCOT

Developer

SMT Houston IV LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

44140 CLODINE 138kV

Data Source

LBNL + Live

No news available for this project.