Chocolate Bayou BESS
BetaActiveBatteryERCOTLBNL
9.9 MW storage in Victoria, TX · In queue since August 2023 · Proposed COD October 2025
9.9 MW
Capacity
1
Components
Battery
2y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
2y 2m
Schedule
5 months past proposed COD
In Study38%
Queue EntryAug 22, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-10-16
Project Details
State
TX
County
Victoria
Region
ERCOT
Developer
Concurrent Holdco. , LLC.
Utility
—
Entity
ERCOT
Data Source
LBNL
No news available for this project.