Texas Bluebonnet Solar
BetaActiveSolarERCOTLBNL
9.72 MW generation in Mclennan, TX · In queue since May 2023 · Proposed COD February 2025
9.72 MW
Capacity
1
Components
Solar
2y 10m
In Queue
IA Executed
IA Status
Signed Aug 2023
Interconnection Timeline
Queue → IA
3 months
IA → COD
1y 6m
Total Duration
3 months
Schedule
14 months past proposed COD
Construction75%
Queue EntryMay 26, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementAug 28, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2025-02-07
Project Details
State
TX
County
Mclennan
Region
ERCOT
Developer
Texas Bluebonnet Solar Partners, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
3370 McGuffey POD 138 kV
Data Source
LBNL
No news available for this project.