Boling Generation (TEF-Due Diligience) — Project Summary

Queue ID
ERCOT-24INR0576
Capacity
400 MW
Technology
Gas
Status
active
Location
Wharton, TX
Region
ERCOT
Developer
Boling Generation
IA Status
Facility Study

Boling Generation (TEF-Due Diligience)

BetaActiveGasERCOTLBNL + Live

400 MW generation in Wharton, TX · In queue since December 2023 · Proposed COD December 2028

400 MW

Capacity

1

Components

Gas

2y 3m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

5 years

Facilities Study50%
Queue EntryDec 4, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-16

Project Details

State

TX

County

Wharton

Region

ERCOT

Developer

Boling Generation

Utility

Entity

ERCOT

Point of Interconnection

43340 Gulftie 138kV

Data Source

LBNL + Live