Marcus Energy Storage — Project Summary

Queue ID
ERCOT-24INR0570
Capacity
201.04 MW
Technology
Battery
Status
active
Location
Brazoria, TX
Region
ERCOT
Developer
Marcus Energy Storage, LLC
IA Status
Facility Study

Marcus Energy Storage

BetaActiveBatteryERCOTLBNL + Live

201.04 MW storage in Brazoria, TX · In queue since June 2023 · Proposed COD September 2027

201.04 MW

Capacity

1

Components

Battery

2y 9m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 3m

Facilities Study50%
Queue EntryJun 7, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-09-01

Project Details

State

TX

County

Brazoria

Region

ERCOT

Developer

Marcus Energy Storage, LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap 138kV 39500 West Columbia Main - 110505 Sweeny Co-Gen LP Ckt 1