Hadrian Energy Storage
BetaActiveBatteryERCOTLBNL + Live
101.2 MW storage in Wharton, TX · In queue since May 2023 · Proposed COD December 2028
101.2 MW
Capacity
1
Components
Battery
2y 10m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 7m
Facilities Study50%
Queue EntryMay 15, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-31
Project Details
State
TX
County
Wharton
Region
ERCOT
Developer
Hadrian Energy Storage, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Line Tap 138kV #43012 NEWGLF60T3_8 - #43190 S_LANE_B138
Data Source
LBNL + Live
No news available for this project.