Wolf Hollow III (TEF-Due Diligence)
BetaActiveGasERCOTLBNL + Live
306.32 MW generation in Hood, TX · In queue since June 2023 · Proposed COD May 2027
306.32 MW
Capacity
1
Components
Gas
2y 9m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 11m
Facilities Study50%
Queue EntryJun 7, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-05-31
Project Details
State
TX
County
Hood
Region
ERCOT
Developer
Wolf Hollow II Power LLC
Utility
—
Entity
ERCOT
Point of Interconnection
1877 Mitchell Bend 345KV
Data Source
LBNL + Live
No news available for this project.