Shaula I BESS
BetaActiveBatteryERCOTLBNL + Live
86.88 MW storage in Dewitt, TX · In queue since July 2023 · Proposed COD December 2025
86.88 MW
Capacity
1
Components
Battery
2y 8m
In Queue
Facility Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
2y 5m
Schedule
3 months past proposed COD
Facilities Study50%
Queue EntryJul 10, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-31
Project Details
State
TX
County
Dewitt
Region
ERCOT
Developer
Shaula Energy Project LLC
Utility
—
Entity
ERCOT
Point of Interconnection
5380 Shaula 345kV
Data Source
LBNL + Live
No news available for this project.