Thomas Cameron BESS
ERCOT-24INR0543BetaActiveBatteryERCOTLBNL + Live
201.52 MW storage in Lampasas, TX · In queue since June 2023 · Proposed COD May 2027
201.52 MW
Capacity
1
Components
Battery
2y 10m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 11m
Facilities Study50%
Queue EntryJun 7, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-05-03
Project Details
State
TX
County
Lampasas
Region
ERCOT
Developer
Thomas Cameron BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 3424 BUCKHORN SWITCH - 3422 KILLEEN SWITCH
Data Source
LBNL + Live
No news available for this project.