Thomas Cameron BESS — Project Summary

Queue ID
ERCOT-24INR0543
Capacity
201.52 MW
Technology
Battery
Status
active
Location
Lampasas, TX
Region
ERCOT
Developer
Thomas Cameron BESS LLC
IA Status
Facility Study

Thomas Cameron BESS

ERCOT-24INR0543BetaActiveBatteryERCOTLBNL + Live

201.52 MW storage in Lampasas, TX · In queue since June 2023 · Proposed COD May 2027

201.52 MW

Capacity

1

Components

Battery

2y 10m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 11m

Facilities Study50%
Queue EntryJun 7, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-05-03

Project Details

State

TX

County

Lampasas

Region

ERCOT

Developer

Thomas Cameron BESS LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 345kV 3424 BUCKHORN SWITCH - 3422 KILLEEN SWITCH

Data Source

LBNL + Live

No news available for this project.