Kinney County Energy
BetaActiveBatteryERCOTLBNL + Live
101.2 MW storage in Kinney, TX · In queue since March 2023 · Proposed COD May 2027
101.2 MW
Capacity
1
Components
Battery
3 years
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 2m
Facilities Study50%
Queue EntryMar 27, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-05-15
Project Details
State
TX
County
Kinney
Region
ERCOT
Developer
Kinney County Energy, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV 8252 Brackett4A - 78255 L_PINTCR8_1Y
Data Source
LBNL + Live
No news available for this project.