Padua Grid BESS Unit 2 — Project Summary

Queue ID
ERCOT-24INR0533
Capacity
150.94 MW
Technology
Battery
Status
active
Location
Bexar, TX
Region
ERCOT
Developer
Padua Grid, LLC
IA Status
IA Executed

Padua Grid BESS Unit 2

ERCOT-24INR0533BetaActiveBatteryERCOTLBNL + Live

150.94 MW storage in Bexar, TX · In queue since June 2023 · Proposed COD March 2026

150.94 MW

Capacity

1

Components

Battery

2y 10m

In Queue

IA Executed

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

2y 9m

Schedule

0 months past proposed COD

Construction75%
Queue EntryJun 7, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2026-03-31

Project Details

State

TX

County

Bexar

Region

ERCOT

Developer

Padua Grid, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

5395 Sommers 138kV

Data Source

LBNL + Live

Linked EIA Plant

Padua 2

EIA Plant ID: 68913

View Plant
No news available for this project.