Padua Grid BESS Unit 2
ERCOT-24INR0533BetaActiveBatteryERCOTLBNL + Live
150.94 MW storage in Bexar, TX · In queue since June 2023 · Proposed COD March 2026
150.94 MW
Capacity
1
Components
Battery
2y 10m
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 9m
Schedule
0 months past proposed COD
Construction75%
Queue EntryJun 7, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2026-03-31
Project Details
State
TX
County
Bexar
Region
ERCOT
Developer
Padua Grid, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
5395 Sommers 138kV
Data Source
LBNL + Live
Linked EIA Plant
Padua 2
EIA Plant ID: 68913
No news available for this project.