Roost Energy Storage
BetaActiveBatteryERCOTLBNL + Live
102.36 MW storage in Scurry, TX · In queue since January 2023 · Proposed COD September 2027
102.36 MW
Capacity
1
Components
Battery
3y 2m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 8m
Facilities Study50%
Queue EntryJan 30, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-09-13
Project Details
State
TX
County
Scurry
Region
ERCOT
Developer
Bluff Creek Energy Storage LLC
Utility
—
Entity
ERCOT
Point of Interconnection
KNDRSACRC Bus #11130 to Knapp Substation Bus #1310
Data Source
LBNL + Live
No news available for this project.