Rogers Draw BESS
ERCOT-24INR0514BetaActiveBatteryERCOTLBNL + Live
145.55 MW storage in Gillespie, TX · In queue since January 2023 · Proposed COD June 2026
145.55 MW
Capacity
1
Components
Battery
3y 3m
In Queue
IA Executed
IA Status
Signed Feb 2024
Interconnection Timeline
Queue → IA
1y 1m
IA → COD
2y 4m
Total Duration
1y 1m
Construction75%
Queue EntryJan 3, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementFeb 28, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2026-06-30
Project Details
State
TX
County
Gillespie
Region
ERCOT
Developer
ROGERS DRAW ENERGY STORAGE, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
7751 Headwaters substation 138kV
Data Source
LBNL + Live
No news available for this project.