Young Wind II SLF
BetaActiveWindERCOTLBNL
152.28 MW generation in Young, TX · In queue since May 2023 · Proposed COD March 2026
152.28 MW
Capacity
1
Components
Wind
2y 10m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 10m
Schedule
1 months past proposed COD
Facilities Study50%
Queue EntryMay 3, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-03-08
Project Details
State
TX
County
Young
Region
ERCOT
Developer
Young Wind II, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Oncor's Thomas Price Station (#11523)
Data Source
LBNL
No news available for this project.