Corralitos Wind 1
ERCOT-24INR0505BetaActiveWindERCOTLBNL + Live
196.1 MW generation in Zapata, TX · In queue since January 2023 · Proposed COD December 2027
196.1 MW
Capacity
1
Components
Wind
3y 3m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 11m
Facilities Study50%
Queue EntryJan 30, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-01
Project Details
State
TX
County
Zapata
Region
ERCOT
Developer
Vaquero Wind Energy, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 80225 CENIZO7C - 80307 DELSOL7C (New ETT Tiempo Substation)
Data Source
LBNL + Live
No news available for this project.