Fort Watt Storage
BetaActiveBatteryERCOTLBNL
205.4 MW storage in Tarrant, TX · In queue since January 2023 · Proposed COD April 2027
205.4 MW
Capacity
1
Components
Battery
3y 2m
In Queue
IA Executed
IA Status
Signed Aug 2024
Interconnection Timeline
Queue → IA
1y 7m
IA → COD
2y 8m
Total Duration
1y 7m
Construction75%
Queue EntryJan 3, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementAug 28, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2027-04-20
Project Details
State
TX
County
Tarrant
Region
ERCOT
Developer
Fort Watt Storage, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV 1933 Kennedale - 2208 Mansfield
Data Source
LBNL
No news available for this project.