Indigo Storage — Project Summary

Queue ID
ERCOT-24INR0496
Capacity
60 MW
Technology
Battery
Status
active
Location
Fisher, TX
Region
ERCOT
Developer
Innovative Solar 245, LLC
IA Status
Facility Study

Indigo Storage

BetaActiveBatteryERCOTLBNL + Live

60 MW storage in Fisher, TX · In queue since December 2022 · Proposed COD September 2027

60 MW

Capacity

1

Components

Battery

3y 3m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 9m

Facilities Study50%
Queue EntryDec 15, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-09-17

Project Details

State

TX

County

Fisher

Region

ERCOT

Developer

Innovative Solar 245, LLC

Utility

Entity

ERCOT

Point of Interconnection

tap 345 kV 68001 Claytonville _x0013_ 68004 Phantom Hill Circuit 2

Data Source

LBNL + Live

No news available for this project.