Barbers Hill BESS
BetaActiveBatteryERCOTLBNL
307.72 MW storage in Chambers, TX · In queue since January 2023 · Proposed COD July 2027
307.72 MW
Capacity
1
Components
Battery
3y 2m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 6m
Facilities Study50%
Queue EntryJan 17, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-07-15
Project Details
State
TX
County
Chambers
Region
ERCOT
Developer
Black Mountain Energy Storage II
Utility
—
Entity
ERCOT
Point of Interconnection
40850 JORDAN 345kV
Data Source
LBNL
No news available for this project.