Forts Trail BESS 2
BetaActiveBatteryERCOTLBNL + Live
201.2 MW storage in Taylor, TX · In queue since February 2023 · Proposed COD July 2028
201.2 MW
Capacity
1
Components
Battery
3y 1m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 5m
Facilities Study50%
Queue EntryFeb 20, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-07-25
Project Details
State
TX
County
Taylor
Region
ERCOT
Developer
JC Central Bluff, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
11406 Central Bluff Switch 345 kV
Data Source
LBNL + Live
No news available for this project.