Forts Trail BESS 2 — Project Summary

Queue ID
ERCOT-24INR0488
Capacity
201.2 MW
Technology
Battery
Status
active
Location
Taylor, TX
Region
ERCOT
Developer
JC Central Bluff, LLC
IA Status
Facility Study

Forts Trail BESS 2

BetaActiveBatteryERCOTLBNL + Live

201.2 MW storage in Taylor, TX · In queue since February 2023 · Proposed COD July 2028

201.2 MW

Capacity

1

Components

Battery

3y 1m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

5y 5m

Facilities Study50%
Queue EntryFeb 20, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-07-25

Project Details

State

TX

County

Taylor

Region

ERCOT

Developer

JC Central Bluff, LLC

Utility

Entity

ERCOT

Point of Interconnection

11406 Central Bluff Switch 345 kV

Data Source

LBNL + Live

No news available for this project.