Rutile BESS
ERCOT-24INR0485BetaActiveBatteryERCOTLBNL + Live
100.65 MW storage in Runnels, TX · In queue since January 2023 · Proposed COD March 2028
100.65 MW
Capacity
1
Components
Battery
3y 3m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 2m
Facilities Study50%
Queue EntryJan 23, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-03-31
Project Details
State
TX
County
Runnels
Region
ERCOT
Developer
Rutile BESS, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 6340 BALLINGER - 60399 WEISS
Data Source
LBNL + Live