Lupinus Solar 3 — Project Summary

Queue ID
ERCOT-24INR0484
Capacity
100.8 MW
Technology
Solar
Status
active
Location
Franklin, TX
Region
ERCOT
Developer
Lupinus Solar 2, LLC
IA Status
Facility Study

Lupinus Solar 3

BetaActiveSolarERCOTLBNL

100.8 MW generation in Franklin, TX · In queue since September 2023 · Proposed COD September 2026

100.8 MW

Capacity

1

Components

Solar

2y 6m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3 years

Facilities Study50%
Queue EntrySep 23, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-09-21

Project Details

State

TX

County

Franklin

Region

ERCOT

Developer

Lupinus Solar 2, LLC

Utility

Entity

ERCOT

Point of Interconnection

1794 Monticello Tap 138 kV